TL;DR: Visual Builder Studio Issues can be the single system of record for a Fusion RICE backlog (Reports, Interfaces, Conversions, Extensions) — but only if everyone touching it tracks work the same way: PM, functional analyst, customer approver, developer. Below is the Epic/Task model, the Rice# and Component custom fields, and the deployment ladder we standardized on across our Fusion engagements in Visual Builder Studio Issues, plus the free, open Python tool we built to load a backlog of dozens or hundreds of RICE items into it in minutes instead of a day of manual data entry. Read this if you’re standing up delivery tracking for a Fusion implementation, or already running one that’s outgrown ad hoc use of Visual Builder Studio Issues.
Tested on / Prerequisites: Verified on Visual Builder Studio 26.10.0. We’ve applied the methodology below across multiple live Fusion implementations, and we test the loader against Visual Builder Studio’s Issues REST API v3 on a live CID tenant. It requires VBS Issues enabled on the project, a Personal Access Token scoped to it, and Python 3 with pandas, openpyxl, and requests.
Every Fusion implementation produces the same kind of backlog: a list of RICE deliverables — Reports, Interfaces, Conversions, Extensions — each moving through functional design, technical design, build, and QA before the customer approves it and the technical team installs it into P1, P2, UAT, SIT, and PROD in sequence. Yet four different roles need to read that same backlog and come away with a different, correct answer: the Project Manager wants status by track and deployment readiness; the Functional Analyst is authoring designs and raising defects; the Customer Approver is signing off entry into each environment; the developer is building, installing, and closing defects.
Visual Builder Studio Issues can hold all of that, but only if everyone records work the same way. Without an agreed structure, consistency is the first casualty: someone types a Component as “P2P” on one Epic and “Procure to Pay” on another, skips a Task, or leaves an environment field stale after an install — and every board or report built on top of the backlog quietly stops being trustworthy. So we wrote the model down as an internal Ways of Working guide, applied it across our Fusion engagements, and — once a backlog grew past a few dozen items — stopped typing it in by hand and started loading it with a small Python tool instead. Both follow below: the methodology first, then the tool.
A shared vocabulary is what keeps a board readable across roles:
| Term | What it means |
|---|---|
| RICE | Reports, Interfaces, Conversions, Extensions — the categories of technical deliverables on a Fusion implementation. Each individual deliverable is a RICE element or RICE item. |
| Epic | The container for one RICE deliverable. The unit the customer signs off on. |
| Task | A unit of work under an Epic — either a build activity (e.g. Development) or a deployment step. |
| Component | The functional/technical track an item belongs to (e.g. P2P, O2C, FA). Used to slice and filter. |
| Rice# | The unique identifier for a deliverable, recorded on its Epic. |
| Release | A target Fusion environment in the promotion path: P1, P2, UAT, SIT, PROD. |
| Board | A visual, column-based view of issues, used to see status at a glance. |
| Sprint | A time-boxed planning period that build Tasks are scheduled into. |
Each delivered RICE item is one Epic. Beneath it sit five fixed child Tasks that carry the build activity through to customer acceptance — Functional Design, Technical Design, Development, Functional QA, Customer QA — plus Defects, raised during QA and linked back to the Epic (or the Development Task) rather than reopening a build Task, so quality reporting stays clean and separate from build-activity status. The Epic represents the deliverable as a whole and is what the customer approves; the Tasks represent the individual activities that progress independently and get planned into sprints.

Here’s what a single deliverable looks like once it’s set up:
Epic: RICE-014 — Print Receivables Transaction
| Field | Value |
|---|---|
| Issue Type | Epic |
| Rice# | RICE-014 |
| Component | O2C (Order-to-Cash) — a receivables transaction print belongs to the order/receivables track |
| Release | P1 (current target environment for first build and playback) |
| Deployment Environment | P1 |
| Deployment Done? | Unchecked (approved for P1, not yet installed) |
| Summary | Print Receivables Transaction — formatted transaction print for the receivables process |
Child Tasks under this Epic: Functional Design (define the print layout, data fields, and triggering rules), Technical Design (BI Publisher template approach, data model, integration points), Development (build and unit-test the report and template), Functional QA (validate output against the design), Customer QA (customer reviews and accepts the deliverable). As work progresses, each Task moves through its statuses on the Delivery board, and the Epic’s deployment fields advance through each environment as the customer approves and the technical team installs.
Two optional issue types round things out: Story, used only if a team wants agile sizing on a piece of build work (otherwise the five Tasks are sufficient), and Feature, used only when one large RICE deliverable genuinely splits into independently shippable sub-parts. Most deliverables go Epic → Task directly — don’t force a Feature layer where it adds no value.
Two standard fields classify every Epic so the work can be filtered, reported, and routed. Component identifies the functional or technical track — the delivery tracks plus one cross-cutting technical track:
| Component | Use it for |
|---|---|
| P2P | Procure-to-Pay track |
| O2C | Order-to-Cash track |
| R2R | Record-to-Report / general ledger track |
| FA | Fixed Assets track |
| INV | Inventory track |
| CM | Cash Management track |
| Localization | Country/statutory localization work that applies across process areas |
| Infrastructure | Cross-track functional and technical infrastructure components |
Rule of thumb: work in a single functional process uses that track; work that underpins the platform as a whole uses Infrastructure. Release records which environment an issue currently targets — P1 (first build/playback), P2 (second build/playback), UAT (customer validation), SIT (cross-system integration testing), PROD. Release reflects environment context as a single value per issue, not a running history — instead, the deployment fields and each issue’s own audit log capture the full promotion trail.
Deployment moves a deliverable up the P1 → P2 → UAT → SIT → PROD ladder, with the customer approving entry into each environment and the technical team performing the actual install. Two fields on the Epic carry this:
| Field | Meaning |
|---|---|
| Deployment Environment | Single-select — the environment currently being promoted into. |
| Deployment Done? | Checkbox. Unchecked = approved for that environment, not yet installed. Checked = installed. |
Each environment moves through two distinct events, owned by two different roles. First, the Customer Approver sets Deployment Environment to the target and leaves Deployment Done? unchecked. Then the technical team installs and checks it. Finally, when the customer approves the next environment, advance Deployment Environment and clear Deployment Done? again — in the same action, never as two separate steps. Leaving the checkbox checked after the environment changes makes the item read as “already installed” in the new environment when it isn’t, which silently drops it from the technical team’s deployment queue. Because these are standard single-value fields, you can build boards directly on them — for example, “everything approved for P1 but not yet deployed.”
Work is planned through sprints; the backlog is the holding area for everything not yet scheduled. Every Task starts in the backlog and stays there until the team commits it to a specific sprint — never both at once. Epics, however, never go into sprints; they span sprints and simply aggregate the progress of their Tasks. Three boards, fed by the same underlying issues, give each role the view it needs:
| Board | Shows | Who relies on it |
|---|---|---|
| Delivery / Build | The five activities by status | Analysts and developers |
| Deployment / Promotion | Issues grouped by Deployment Environment, split by Deployment Done? | Technical team (what to install) and customer (what to approve next) |
| Defects | Defects by status | Everyone — open quality items by environment or component |
Swimlanes by Component or Rice# let a team slice any board by track, scoped either to the active sprint or the wider backlog. So each role’s part in this: the Project Manager monitors progress across Epics and boards, tracking deployment readiness and defect trends; the Functional Analyst authors Functional Design Tasks, performs Functional QA, and raises Defects with clear reproduction detail; the Customer Approver performs Customer QA and approves entry into each environment; the Developer/Technical Team authors Technical Design, performs Development, installs into each environment, and resolves Defects. Everyone should also turn on VBS’s own issue-update email notifications in their profile — otherwise staying current means polling boards instead of receiving alerts.
VBS supports several relation types; we standardize on a small set so the picture stays readable: Implements/Implemented By ties an activity Task to its parent Epic; Depends On/Dependency Of handles build sequencing, within an Epic or across Epics; Requires/Required By is reserved for genuine hard blockers, used sparingly; Discovered While Testing links a Defect back to the deliverable whose testing surfaced it; Relates To is a general, informational link. VBS records these relations and makes them navigable, but doesn’t enforce them — an unmet dependency doesn’t block work; it only informs planning.
A few disciplines keep the system reliable as the backlog grows:
A few limits are also worth knowing up front. Epics never go into sprints, so burn-down happens at the Task level and the Epic simply aggregates it. Boards display child issues (Tasks, Defects), not Epics, which is why deployment shows up on the fields the Tasks/Epic carry. And deployment fields show current state only — the full change history lives in each issue’s own audit trail, not in a report built for bulk historical tracking across many issues at once. In short, it’s a living model: as reporting needs evolve, we revisit and update it.
That model works cleanly when someone enters a handful of Epics by hand. However, it breaks down the moment a new engagement hands over a backlog of 40, 80, or 120 RICE items as a spreadsheet: creating six issues per row (1 Epic + 5 Tasks) one field at a time in Visual Builder Studio Issues is slow, and it’s exactly where someone mistypes a Component or skips a Task. So we open-sourced the Python tool we use instead: vbs-uploader, free to clone and run against your own VBS tenant.
mkdir -p ~/vbs-uploader && cd ~/vbs-uploader
python3 -m venv venv
source venv/bin/activate
pip install --upgrade pip
pip install pandas openpyxl requests
Authenticate without leaving the token in shell history:
read -s -p "Paste VBS token: " VBS_TOKEN
export VBS_TOKEN
read -s hides the token as it’s typed, so only the bare export VBS_TOKEN command — never the token itself — lands in ~/.zsh_history. Generate the token from VB Studio → avatar → Preferences → Personal Access Tokens, scoped to the target project, or every call comes back 403. Note that --base-url isn’t the URL the VB Studio UI shows you: that one carries a #projects/... fragment, and the server never receives anything after #. The real base URL instead has the shape https://<host>/<org>/rest/<org>_<project>_<id>, with the identifier from Project Administration → Properties → Identifier.
The repo ships a sample_issues.xlsx with five rows — three that load cleanly and two deliberately broken ones, so you can see the resolution logic before ever pointing the script at a real backlog:
| Summary | Description | Component | Release | Rice# |
|---|---|---|---|---|
| Print Receivables Transaction | Formatted transaction print for the receivables process | O2C | P1 | RICE-014 |
| Supplier Invoice Auto-Match Extension | Custom matching rules for 3-way match exceptions | P2P | UAT | RICE-021 |
| GL Journal Import Interface | (blank) | R2R | (blank) | RICE-030 |
| Asset Depreciation Report | Custom depreciation schedule report | FixedAssets-Bogus | P2 | RICE-042 |
| (blank) | No summary provided on purpose | INV | SIT | RICE-099 |
Only Summary and Component are required; Description and Release may be blank. Run --discover first to confirm the tenant’s real Components/Releases/defaults against the sample above, then dry-run it:
python3 vbs_issue_uploader.py --base-url <base-url> --discover
python3 vbs_issue_uploader.py --base-url <base-url> --excel sample_issues.xlsx --dry-run
O2C is a real Component, P1 a real Release. Creates 1 Epic (Summary prefixed to RICE-014 - Print Receivables Transaction, Component=O2C, Release=P1, customFields.RiceNumber=RICE-014) plus its 5 child Tasks (Functional Design, Technical Design, Development, Functional QA, Customer QA), each summary based on that same prefixed title with its activity name appended.Component=P2P, Release=UAT. 1 Epic + 5 Tasks.Component=R2R is real, and Release is blank, so the script falls back to the product’s defaultRelease (P1) instead of guessing or rejecting the row. 1 Epic + 5 Tasks.FixedAssets-Bogus isn’t a Component name the tenant actually has (the real one is FA). Logged with the reason, nothing created.So a --limit 1 smoke test creates exactly one Epic (RICE-014) with its 5 Tasks nested under it; the full run against this sample file creates 3 Epics and 15 Tasks — 18 issues in total — and writes a sample_issues.results.csv next to the Excel file recording which rows it created, skipped, or failed, along with the resulting issue IDs. Swap in a real backlog and the same three commands (--discover → --dry-run → full run) scale to however many rows it has.
Two REST behaviors matter once you go past the sample file. First, POST /issues/v3/issues requires seven fields (summary, product, component, severity, status, priority, release), and severity/status/priority/release each need both id and value — the API silently treats a lone id as missing. Second, linking each Task to its Epic isn’t one call: POST .../subissues returns an HTTP 500 on our tenant when you ask it to create and link in one request, so instead the script creates the Task via POST /issues/v3/issues and links it with PUT /issues/v3/issues/{taskId}/parentissue. It also sets customFields.DeploymentEnv to the Epic’s own Release at creation time on every Epic and Task — not a real feature yet (it isn’t an Excel column), but a required workaround for a platform bug where an untouched DeploymentEnv sticks at "---" and then rejects any later write (see Gotchas).
A companion vbs_export_issues.py pulls every issue on the project back into Excel — id, type, Component/Release/status names, cf_RiceNumber, cf_DeploymentEnv, parent issue id, and more, sorted by id so each Epic naturally groups with its Tasks. A cleanup_vbs_test_issues.py closes out test/POC issues created while validating the loader, since there’s no delete endpoint for issues in this API.
Process discipline (the part no API enforces for you):
API and tooling gotchas (confirmed by live testing, not assumptions):
create() requires all seven fields or you get a 400 naming exactly which one is missing.severity/status/priority/release need both id and value — the API silently rejects id alone as if it were absent.repository.customFields does — always --discover first.POST .../subissues doesn’t reliably create-and-link a Task in one call — create it, then PUT .../parentissue.DeploymentEnv untouched at creation poisons the issue at "---"; every later write to that field then fails. This looks like a genuine platform bug — the write-path rejects the read-path’s own default — and is worth an Oracle Support SR, since it can affect issues created by hand in the UI too.Status=CLOSED + Resolution=WONTFIX.GET on the issue confirms it’s already there server-side.--discover output’s Components and Releases against your Ways of Working vocabulary before loading anything for real.--dry-run output against the sample table above: three rows should resolve cleanly, and the loader should skip the other two, each with a stated reason.--limit 1 smoke test, open the Epic in VB Studio and confirm all 5 Tasks are nested under it and Rice# is populated.GET on a created issue to confirm customFields.RiceNumber round-tripped as a flat string, independent of what the UI currently shows.vbs_export_issues.py afterward and cross-check the export against the source backlog, row for row.A documented Epic/Task model with two custom fields (Rice#, Component) and a disciplined deployment ladder is what lets four different roles read the same Fusion delivery backlog in Visual Builder Studio Issues and get the right answer out of it. At real backlog scale, loading it by hand is where that discipline breaks down first — which is why we load it with a free, open script instead, turning a day of manual data entry into a --discover → --dry-run → --limit 1 → full-run sequence that takes minutes and never mistypes a Component.
Standing up delivery tracking for your own Fusion implementation in Visual Builder Studio Issues, or watching an ad hoc setup buckle under a growing backlog? We’ve built and run this exact Ways of Working across multiple enterprise engagements, and we can do the same for you. Reach out at info@cidsolutions.co.il or WhatsApp — let’s get it solved.